Timeline

The following table illustrates the major target dates for relocating LSC occupants to facilitate the LSC Revitalization and Expansion Project.  Please note:  these dates could change due to unforeseen delays.

December 2012

  • The contractor mobilized with trailers and fencing
  • Utility work started on the Plaza near the RAMtech entrance
  • Exterior work on the west side will begin

January 2013

  • The Senate Chambers, Curfman Gallery, and the Sutherland Sculpture Garden will be taken off-line
  • Demolition on the Solarium, Senate Chamber, and Curfman Gallery will begin (expected completion of early Spring 2013)

May 2013

  • Affected offices will be moved by the end of May 2013.

August 2013

  • The renovated portion of the Student Center is anticipated to open for Fall semester 2014.

November 2013

  • Surrounding building landscape work is anticipated to be complete.

 

Emergency evacuation plans can be found here.