The Lory Student Center’s renovation timeline began in 2010. It is estimated that the Master Plan renovation project will be completed Fall 2014. For a complete report, you can download Concept Design Report (60 megs) developed by Perkins + Will.
March 2010 Phase II LSC Master Plan Complete
April 2010 Student Fee Review Board approved $6M theatre renovation with no fee increase requested
September 2010 Presentation to Lory Student Center Governing Board
October 2010 Presentation to Student Fee Review Board
Jan/Feb/March 2011 Presentations to student groups regarding theatre and Master Plan renovations
February 2011 Begin design development of theatre
February 2011 LSCGB has the scoop event
April 4th, 2011 Presentation to Student Fee Review Board
April/May 2011 Theatre renovation project bids and award
June 2011 Theatre renovation begins
June 2012 Theatre renovation complete
Fall 2012 50th anniversary celebration
Spring 2013 LSC master plan renovation start date
Fall 2014 Estimated completion date for Master Plan renovation project (fee not implemented until project is completed)